Skip to content

Milestones

List view

  • This is just a bucket to hold all the tasks that we would like to implement sometime in the future.

    Overdue by 7 year(s)
    Due by January 1, 2019
    11/11 issues closed
  • These are features which are NICE to have for first release but not REQUIRED. Due date set to the start of O-Week.

    Overdue by 7 year(s)
    Due by September 1, 2018
    2/2 issues closed
  • This is a go/no go date to have these REQUIRED features for the first official release.

    Overdue by 7 year(s)
    Due by August 20, 2018
    7/7 issues closed
  • These are features which would be NICE to have for MVP release, but not REQUIRED. Tentative date set to the MVP release date.

    Overdue by 7 year(s)
    Due by July 1, 2018
    7/7 issues closed
  • This is what we defined as MUST-HAVE for MVP (minimum viable product). Our go/no go date for distribution in July is currently set to be June 25.

    Overdue by 7 year(s)
    Due by June 25, 2018
    18/18 issues closed