Casal2 Project Status

Current Status

Casal2 has issued a release in June 2024 (2024.06). The project is currently seeking further funding to develop new features and maintain the project.

Planned work for July 2021 to June 2022

(last updated: 5 Oct 2021)

A list of planned work is being put together and may include the following:

  • review efficiency with respect to code optimisation and memory usage;
  • design, document, and implement options that are available in CASAL (e.g., selectivity functions, stock-recruitment relationships);
  • design, document, and implement q-ratios functionality;
  • review and edit the User Manual;
  • review and update the R package; and
  • develop training materials.

A Casal2 workshop was held online on 5 October 2021. This workshop described the project status and recent work and provided information on planned work.

Planned work for July 2020 to June 2021

(last updated: 6 Aug 2020)

A list of planned work is being put together and may include the following:

  • review and refine project management framework;
  • evaluate collaboration and project communication tools (i.e., is Casal2 accessible?);
  • initiate Casal2 Advisory Group;
  • review and test the tagging functionality;
  • review Casal2 efficiency with respect to code optimisation and memory usage;
  • design, document, and implement options that are available in CASAL (e.g., selectivity functions, stock-recruitment relationships);
  • design, document, and implement q-ratios and weight-frequencies functionality;
  • review the design of the existing length based functionality and prioritise development;
  • review unit tests (coverage and efficacy) and document best practice;
  • evaluate third-party MCMC algorithms; and
  • develop training materials.

In-work for July 2020 to June 2021

(last updated: 6 Aug 2020)

Work in progress includes:

  • testing and validating with simulated data, e.g., the simulated data from the NOAA Fisheries Stock Assessment Model Comparison Project;
  • extracting the Hessian from CppAD minimisation;
  • reviewing and editing the User Manual;
  • reviewing the R package; and
  • more review and testing of the retained/discarded catch functionality.

Planned work for July 2019 to June 2020

(last updated: 6 Aug 2020)

Planned work included:

  • design and develop the project management framework for enabling collaboration and ongoing maintenance and support;
  • set up project hosting and CI/CD on NIWA-managed resources;
  • determine project status including reviewing history of Casal2 development, and reviewing all available documentation;
  • determine project state including reviewing source code and issues in the repository;
  • enable user and developer engagement;
  • identify and document a tractable set of useful (common to multiple age-based assessments of NZ deepwater stocks) functionality required in Casal2 V1.0;
  • develop and construct a set of Test Cases models in CASAL and Casal2 that include commonly used options for NZ deepwater stock assessments;
  • document, test, and validate the functionality used for the Test Cases;
  • review the MCMC functionality;
  • review the projection functionality;
  • review and update the User Manual;
  • review and update the R package; and
  • create versioned docker images for reproducibility.