Part of: #8
Runs in parallel with: Phase 2 (#3) individual contributor outreach (both close Sep 20)
Feeds: Pre-Switch Sign-off Gate (#5)
Target window: Aug 21 – Sep 20, 2026 (30 days, fixed). Hard project deadline is 2026-09-30 (see epic #8). This 30-day window cannot be compressed. Phase 3 runs in parallel with the tail of Phase 2 individual contributor outreach — both close Sep 20.
Goal
Give the broader community — downstream users, integrators, and the public — a formal opportunity to review and comment on the proposed license change before it takes effect.
Treatment of pre-switch history vs post-switch code
The proposed switch release/commit, or the criteria for selecting it
Summary of consent coverage and any remaining removals/rewrite plans (from Phase 2)
Dependency / distribution-boundary decisions from Phase 1
Comment window start/end dates with timezone (Aug 21 – Sep 20, 2026), the official feedback channel, the decision criteria, and who makes the go/no-go call
Tasks
Draft the RFC/notice content during Phase 2 (in parallel, not after) so it's ready to post Aug 21
Post a formal RFC / Notice and Comment on the cBioPortal GitHub with a 30-day comment window (Aug 21–Sep 20), containing all required notice contents above
Announce on the cBioPortal mailing list with a link to the GitHub RFC
Announce in relevant community channels (Slack, Google Groups, etc.)
Actively monitor and respond to community questions during the 30-day window
Summarize feedback received and document any issues raised
Make a go/no-go decision at the end of the comment period (by Sep 20)
Definition of Done
30-day window has closed (Sep 20). Feedback summary published. Core team has made a documented go/no-go decision to proceed to the sign-off gate (#5) and then Phase 4.
Phase 3: Community Feedback & Notice Period
Part of: #8
Runs in parallel with: Phase 2 (#3) individual contributor outreach (both close Sep 20)
Feeds: Pre-Switch Sign-off Gate (#5)
Target window: Aug 21 – Sep 20, 2026 (30 days, fixed). Hard project deadline is 2026-09-30 (see epic #8). This 30-day window cannot be compressed. Phase 3 runs in parallel with the tail of Phase 2 individual contributor outreach — both close Sep 20.
Goal
Give the broader community — downstream users, integrators, and the public — a formal opportunity to review and comment on the proposed license change before it takes effect.
Required notice contents
Tasks
Definition of Done
30-day window has closed (Sep 20). Feedback summary published. Core team has made a documented go/no-go decision to proceed to the sign-off gate (#5) and then Phase 4.