Part of: #8
Blocked by: Phase 3 (#4) — community comment period must close first
Blocks: Phase 4 (#6) — the Switch Commit must not start until this gate is signed
Target window: Sep 20–23, 2026. Hard project deadline is 2026-09-30 (see epic #8). To keep this window short, assemble the record continuously throughout Phases 1–3 rather than starting it here — this issue should be a fast formality (consolidate + sign), not a fresh assembly exercise. Team lead consents (deadline Aug 31 via #3) should be in hand well before this gate.
Goal
Consolidate the entire relicensing record into a single, auditable, signed artifact before the Switch Commit, so the rationale isn't scattered across phase issues and the switch is defensible under later audit.
Immutable record: commit the record into the repo (e.g. docs/relicensing/) so the decision record lives in git history alongside the switch itself; this issue links to it.
Named signatories: the team lead of the cBioPortal team at each contributing organization that holds the bulk of the copyright — MSKCC, DFCI, PMCC, CHOP, The Hyve, SE4BIO (per RFC 86 Phase 2: Contributor Outreach & Consent #3). Record explicitly that team lead consent was obtained at the team-lead level, not through formal institutional legal/tech-transfer review — this is a documented, deliberate choice (see CLAUDE.md Decisions) made to fit the project timeline.
Private records (signed originals, not committed to this public repo)
Reference to the private records folder (signed originals) above
Definition of Done
The consolidated record is published and committed to the repo, every line item above is linked and closed, and the named signatories have signed off. Only then may Phase 4 (#6) begin.
Pre-Switch Sign-off Gate
Part of: #8
Blocked by: Phase 3 (#4) — community comment period must close first
Blocks: Phase 4 (#6) — the Switch Commit must not start until this gate is signed
Target window: Sep 20–23, 2026. Hard project deadline is 2026-09-30 (see epic #8). To keep this window short, assemble the record continuously throughout Phases 1–3 rather than starting it here — this issue should be a fast formality (consolidate + sign), not a fresh assembly exercise. Team lead consents (deadline Aug 31 via #3) should be in hand well before this gate.
Goal
Consolidate the entire relicensing record into a single, auditable, signed artifact before the Switch Commit, so the rationale isn't scattered across phase issues and the switch is defensible under later audit.
Make it enforceable and durable
Blocked bythis issue.docs/relicensing/) so the decision record lives in git history alongside the switch itself; this issue links to it.Private records (signed originals, not committed to this public repo)
Any legal correspondence and other documents containing sensitive details are stored privately at https://drive.google.com/drive/folders/1pGq4cS1S_gKhCsOsIO7sTEo5IQ9i4pTI (Google Drive, access-restricted). The public record links to this folder as the location of record.
The record (public index) must link
Definition of Done
The consolidated record is published and committed to the repo, every line item above is linked and closed, and the named signatories have signed off. Only then may Phase 4 (#6) begin.